Thai Binh – Ham Rong Project

  • Investor: PetroVietnam Gas (PV Gas)
  • Main contractor: Petroleum Equipment Assembly & Metal Structure Joint Stock Company (PVC-MS)
  • Subcontractor: Chan Hung JSC
  • Content: Wrap the joints for the gas collection and distribution system in Thai Binh - Ham Rong field.
  • Construction time: From 3rd Jan, 2015 to 11th Feb, 2015




Image1: Surface Cleaning

Image 2:  Wrap oil pipe